Background
May21 Pty Ltd and FEC May22 Pty Ltd (collectively, Developer) entered into an amended AS4300-1995 ‘design and construct’ contract with Multiplex Constructions Pty Ltd (Builder) for Towers 3 and 4 (Works) of West Side Place at 250 Spencer Street, Melbourne (Project). The contract price for the whole of the Stage 2 Works was approximately $660 million plus GST.
The Developer engaged the fourth respondent, the relevant building surveyor (RBS) to assess the application for a staged building permit to carry out the Works. The RBS adopted the entire GST inclusive contract price as its “estimate” of the cost of the of the Works. In doing so, the RBS relied on guidance from the Victorian Building Authority (VBA) to this effect.
The Developer disputed the RBS’s adoption of the entire contract price as the “estimate” for the purpose of calculating the applicable levy. Central to the Developer’s position was the submission that there was no prohibition on other relevant information being considered, in addition to the contract price. This could include, for example, trade breakdowns and other material demonstrating that certain items in the contract price were not ‘building work’ within the meaning of the Act, and therefore not leviable.
The Developer was initially unsuccessful in the Building Appeals Board. In the first appeal, the Supreme Court of Victoria found in favour of the Developer. It held that the whole contract price was the price for both building work and non-building work under the Act, and while the RBS must “have regard” to the contract price for estimating the whole of the building work, there was no prohibition on the RBS considering other matters, in addition to the contract price.
The VBA made an application seeking leave to appeal the decision of the Supreme Court of Victoria.
For a summary of the decision of the Supreme Court of Victoria, click here.